4.2 Problem solving
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

4.1 Dealing with risk
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

3.3 Managing conflict
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

3.2 Communicating with the project team and other stakeholders
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

3.1 Introduction
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

2.8 Controlling changes to the project
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

2.7 Tracking progress
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

2.6 Maintaining balance
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

2.5 Project meetings schedule
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

2.4 Project status reports
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

2.3 Interdependency of systems
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

2.2 Monitoring as control
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

1.4 Resourcing the project
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

1.3 Motivating and preparing staff
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

1.2 Defining team responsibilities
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

1.1 The transition from planning to action
Day-to-day monitoring of a project is essential to ensure that work is progressing according to the plan, and it will often be necessary to review and revise the plan as circumstances change. This unit will introduce some of the key techniques that help managers to monitor and control projects, and consider what approaches work best in particular circumstances.
Author(s): The Open University

License information
Related content

Except for third party materials and otherwise stated (see http://www.open.ac.uk/conditions terms and conditions), this content is made available under a http://creativecommons.org/licenses/by-nc-sa/2

Environmental Justice and Human Rights in the Aftermath of Katrina
Notre Dame OpenCourseware (OCW) offers free educational resources for the course "Environmental Justice and Human Rights in the Aftermath of Katrina" in the Center for Social Concerns. This seminar will explore how impoverished communities in Louisiana are recovering from Hurricane Katrina. We will explore the historical, political, and economic issues that created a culture of inequality in these areas. The course will also critically reflect on the nexus between social stratification, povert
Author(s): Cynthia Toms Smedley

License information
Related content

Copyright 2012, by the Contributing Authors

Harmonization methodology for metadata models
Metadata allows systems, applications and users to manage and access resources without a need for interaction with the resource itself. For this reason, the administration and exchange of metadata is a central activity in systems that manage learning objects. Metadata considerations are fundamental when creating interoperable e-learning tools, and metadata standards have been among the very first learning technology standards to mature. This deliverable analyses a number of existing metadata spe
Author(s): Nilsson Mikael,Naeve Ambjörn,Duval Erik,Johnston

License information
Related content

Rights not set

A Conceptual Approach to Studying the Learning Process - with a Special Focus on Knowledge Creation
In this paper we present a conceptual approach to the study and analysis of learning processes with emphasis on the knowledge-creating types of learning processes that often occur in workplace learning.,Research report of the ProLearn Network of Excellence (IST 507310), Deliverable 5.3
Author(s): Naeve Ambjörn,Nilsson Mikael,Palmér Matthias,Wes

License information
Related content

Rights not set

Political Perspectives to State Censorship of Literature
Peter McDonald and David Robertson discuss the idea of state censorship, especially Apartheid era South Africa, looking at the political perspectives and implications of state censorship of literature
Author(s): Peter McDonald and David Robertson

License information
Related content

http://creativecommons.org/licenses/by-nc-sa/2.0/uk/